Сегодня на перегоне «Апановка - Казанбасы» работниками Северной дирекции проведено финальное технологическое «окно» InConKZ по укладке пути в этом сезоне.
InCon KZ team renewed 30.3 km of track in the last summer month.
Works included three sections: Passing loop 117 – Atassu and Kyzylzhar – Tuyemoynak in Karagandy region, and Apanovka - Kazanbassy in Kostanay region.
The plan of August is fulfilled 100%
InCon KZ team renewed 30.3 km of track in the last summer month.
Works included three sections: Passing loop 117 – Atassu and Kyzylzhar – Tuyemoynak in Karagandy region, and Apanovka - Kazanbassy in Kostanay region.
Along the line of the Southern Directorate 14.3 km of track was rehabilitated. The Northern Directorate have laid 16 km of new track panel.
From the beginning of works, 145.9 km of track have been renewed by the Southern, Western and Northern Directorates in total in the Southern and Northern Kazakhstan regions.
Overall, 28 track possessions for track laying have been carried out in June by InCon KZ team. Works have been performed in Almaty, Kyzylorda and Kostanay regions.As for track overhaul, we rehabilitated 39.5 km of track, having general plan of 38.5 km.
Since the beginning of the season, all our directorates have shown good work at their sites in Almaty, Kyzylorda and Kostanay Regions. Till the end of May, under the contract, we planned to overhaul 28.4 km of the railway.
Actual implementation amounted to 35.4 km.
The result worthy of the InConKZ team.